Arklow Bank Wind Park is a 25 megawatt offshore wind farm generating electrical power for the Wicklow region in Ireland. It is the first offshore wind farm in Ireland, and the world's first erection of wind turbines rated over 3megawatts each. It is located on the Arklow Bank, a shallow water sandbank in the Irish Sea, around off the coast of Arklow with an area of .〔(Irelands Offshore Wind Power ), University of Delaware〕 The project is being co-developed by Airtricity and GE Energy. In 2002, Airtricity obtained an offshore lease for a 520 MW offshore wind farm. The first phase of the project, commissioned in June 2004, consists of seven GE 3.6-megawatt generators. They were installed by the Danish offshore wind farms services provider A2SEA.〔 〕 Power cables were laid by Five Oceans Services (now SIEM Offshore Contractors),〔 (【引用サイトリンク】title= Arklow Bank Offshore Wind Farm ) 〕 and construction of the turbines themselves was based out of Rosslare Port. All of the turbines have a height of and height to top of blade of . The blade length is and each turbine has three blades. Each turbine weights 290 tonnes. They use steel monopole foundations driven in by a hydraulic hammer and each turbine has a landing platform for boat access. They are spaced apart. Generated electricity is fed to ESB Networks distribution grid through the Arklow National Grid Substation.〔 Phase 2 of the Arklow Project was to be developed in partnership with Acciona Energy of Spain. The development was to consist of a further 193 turbines. However, Phase 2 and the planned connection to Eirgrid transmission system was canceled in 2007.〔http://www.airtricity.com/assets/Uploads2/Press-Releases/Offshore-support-press-release1.pdf〕 The project is proposed to a larger scheme which includes a further installation at Bray Head and would see a total of 1620MW generation capacity, almost twice the offshore turbine capacity in operation worldwide as of 2006. The development has elicited local concern that some 420 turbines would also be visible from the Arklow coast while applications have been submitted for further wind banks in excess of 1000MW capacity.〔(Background Note: Wicklow Offshore Wind Farms – Inadequate Permitting Process ), Coastal Concern Alliance]〕 Local consultation about offshore power generation is minimal,〔(Pylon concerns raised with Labour ), Wicklow News〕 but the local tourism association lists the wind farm as part of the Arklow South Beach.〔(Arklow South Beach & Wind Farm ) visitarklow.ie〕 However, despite planning and controversy, the Arklow Bank Wind Farm capacity remains 25MW as of September 2014.〔(Infrastructure ) Arklow & District Chamber〕 ==See also== * List of offshore wind farms *List of offshore wind farms in the Irish Sea * Wind power in Ireland 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Arklow Bank Wind Park」の詳細全文を読む スポンサード リンク
|